Amy Imai Elementary construction (formerly Huff)

2020-21 Construction Projects

(Funded by Measure T)

link to Huff construction postcard
Click here for a postcard describing Huff's projects

Click here for a postcard describing Huff's projects (Spanish/español)

Measure T, the $259 million bond issue passed in 2020, included plans for a variety of projects that will increase safety, efficiency and provide for short-term growth at our schools. 

To receive regular updates by email, please sign up here.

HVAC
Replacement and improvements of HVAC equipment was completed this summer in mechanical closets and in classrooms, offices, MUR across the campus. Our schools’ HVAC systems have been updated to include MERV-13 filters, which is the highest-grade filter available for our units, or air purifiers with filtration ratings at least as high as the MERV-13.   Additionally dampers on all of our units are open to full capacity and will pull in outside air.
 
Security
This summer, work was done to improve perimeter fencing and adding gates to completely enclose campus and fields in order to secure campuses and make COVID screening more efficient. Fencing and gates are ornamental metal to match existing at campus frontage and 6’ high chain link fencing and gates at property lines and back of campus. 

The purpose of fencing is to control points of entry during school hours. It’s important to note that the public will have access to fields outside school hours. The intention is to secure campuses when students are present, and have gates open through a lock management system in the evenings and on weekends. 

Imai will get a new six-foot metal ornamental fencing around the library building, new gate at the office entrance, and six-foot ornamental metal fencing at the end of Classroom wings near the staff parking.

Click here for the perimeter fencing map (user friendly)
Click here for the Bubb/Huff Community Meeting Presentation

Solar
Imai's two solar arrays near the playground structures are almost complete. Not only will these structures support solar panels to save the district $600,000 annually in electrical costs, they will provide much-needed shade.  Some non-heritage trees were removed to make way for the arrays, but MVWSD will replant two native trees for every one removed.

Project start: Summer 2021. Click here for a map of the solar areas. 

Lighting
New lights and/or bollard style light posts to illuminate pedestrians’ path of travel between campus and parking lots will be added. The areas of need are determined by photometric data. This additional lighting is an important safety measure for staff members and guests using the campus in the evenings and winter late afternoons. Project start: Fall 2021

Public Restrooms
Imai will purchase and install prefabricated, standalone toilet buildings. The units would be maintained by the City and may be used afterhours by the public. This is an important security measure to ensure adults are not mixing with children in student restrooms.
Click here for the restroom project presentation

Window Replacement
The District will replace existing, older single pane windows at Huff in 2023.

Additional Permanent Portable
Installation of one 960-sf classroom portable on a permanent concrete foundation including sitework and landscaping is planned for Summer 2022. It will have the standard classroom finish; whiteboard wall, sink and audio-visual system. It will be placed just to the south of portable kinder room #20. Project start: Summer 2022. Click here to view the location of the portable.

One 960 SF standard classroom portable will be installed on a permanent concrete foundation. Location to be determined 


 

2017-19 Classroom Modernization and a New Multi-Use Room

(18-month project funded by Measure G)

Summer 2019 
Accessible ramps were installed at classroom doors. District-owned portable classrooms were refreshed this summer,  meaning they will get new paint, carpet and whiteboards. Unused, leased portable classrooms will shuttered, and removal of these portables will happen in summer 2020.
The school got a new sign in the front. This sign, paid for with Measure G funds, will include accurate school and district names. Funding for construction and capital improvements, like school signs, come from restricted funds that can be used only for that purpose. The District used an innovative approach to piggyback on existing, competitive local government contracts to lower the sign cost and expedite installation.

January 2019
The conversion of the former multi-use room to library and special education rooms is complete. 

During Summer 2018
The classroom modernization, administration office reconfiguration, and expansion of one kindergarten classroom was completed by the end of summer 2018. The modernization and renovation of the existing multi-use room into the new library and two special education classrooms started in Summer 2018 and will be complete by winter 2018. 

Containers to house classroom furnishings and materials during the summer were delivered in mid May and placed in the side parking lots. Improvements to the school parking lot will happened over summer 2018, with the goal of making traffic flow safer and more efficient.

Over the 2017-18 school year
Construction work was concentrated behind the fence on the MUR, which is set to be completed in June. Work was finished on the creation of the MUR site pad, digging of the footings, installation of foundations, and hanging of steel. 


Huff construction chart


The District has worked very hard over the years to do the work, funded by Measure G, to make facilities improvements and renovations at every school a reality.

Click here for the summer construction postcard update, May 12, 2017 (en español)

What each phase will look like (click to enlarge)

Huff Phase map